Tuesday, July 26, 2011

FGHS North Field: Site Preparation - July 26, 2011

video
The excavators are working hard to prepare the soil for the new athletic fields at Forest Grove High School just to the north of the stadium and baseball diamond.

Neil Armstrong: Science Room Construction - July 26, 2011

video
Two pods of Sciecne classrooms at Neil Armstrong have been converted from two classroom spaces to two classroom spaces and a shared lab space. Sheetrock has been applied to the metal studs creating a feeling of the space available.

Harvey Clarke: Site Preparation - Jul;y 26, 2011

video
THe machinery is digging up the hardtop and preparing the site for the construction work to come.

Echo Shaw: Walls and Floors - July 26, 2011

video
You can see the floor of the new section of the cafeteria in this video. The walls are taking shape as well.

Joseph Gale: Site Preparation and Gym Foundation - July 26, 2011

video
The foundation for the gym at Joseph Gale is poured. Work continues on the entire building site to prepare the building's pad.

Monday, July 18, 2011

Joseph Gale: Foundation Work - July 15, 2011

video
In this video, you will see the foundation prep work, pouring the foundations and some finished foundations for the new Joseph Gale building.

Wednesday, July 13, 2011

Echo Shaw: Finishing the Cafeteria Floor - July 13, 2011

video
The foundation for the walls of the new portion of the cafeteria are in place and the floor has been poured. Workers are finishing the surface of the new floor space.

Joseph Gale: Preparation for Gymnasium Floor - July 13, 2011

video
Here is the work on the foundation for the gym floor. This is located in the NE corner of the new building.

Tuesday, July 12, 2011

Neil Armstrong: Science Room Remodel - July 12, 2011


video
This video shows the current progress on the remodel of two Science pods at Neil Armstrong from two separate classrooms in each pod to two classroom spaces with a shared lab space in each pod. The walls are up and the wiring is being done.

Thursday, July 7, 2011

Echo Shaw: Site Preparation and Foundation Work - July 7, 2011

video
The cafeteria has been opened up and the site of the expansion has been prepared. The beginnings of the foundation work has begun as can be seen in the foreground of the video.

Harvey Clarke: Site Preparation - July 7, 2011

video
This video show the site preparation for the first phase of the construction at Harvey Clarke which will include a new cafeteria, soft pay area and hard play area. There will also be changes to the bus loop and some parking.

Wednesday, July 6, 2011

Joseph Gale: Excavation and Grading Work - July 6, 2011

video
The video begins at the Northwest corner of the site showing the machines laying the base pad for the building, moves to Maple Street for the sewer work and finishes with a view from the East side of the construction site.